Project Selection Page of the Integration Wizard — Scheduling Tools

Use this page to select the schedule project from which data is imported and the Cobra project to which it is imported.

This page displays if you are importing project data.

Contents

Field Description
Schedule Project Use this field to select a source project from which you will import data.
Cobra Project Use this field to identify the Cobra project to which the data will be imported. Enter the project name or click to select a project from the lookup. It can take a while to retrieve data for the lookup.

You can only select a project that you have access to modify.

This field becomes blank when you select the Create a new project check box.

Create a new project Select this check box to create a new project. Clicking this check box makes the Cobra Project field blank.

Enter a name for the new project or use the default name that Cobra assigns. The project name must be unique.

Populate only the link table Select this check box if you want the import process to populate the link tables but not load the data into the database.